At present, i'm in charge of arranging work for a dozen engineers and I use an old A3 diary to pre-book their work which is handy because at a glance, anyone can look at the diary page and see them all listed horizontally and their allocated workload, below is an example: -
Engineer I Eng1 I Eng2 I Eng3 I Eng4 I
Monday I Job1 I Job5 I Job6 I Job8 I
Tuesday I Job2 I Job7 I Job12 I Job8 I
Wed I Job3 I Job9 I Job11 I Job8 I
Thurs I Job4 I Job10I Job8 I Job8 I
(the I's are meant to be inline but the editer on here won't allow it)
Moving on, the engineers have now been given Samsung Galaxy tablets to use out in the field so I want to update the way that their workload is recorded, is there a calendar that I can setup an individual calendar for each user, but have a view on mine (or another PC based at my work) that I can look at which will list them all, similar to the above?
The plan is that on a daily basis, I will manually sync the diary on my PC with their tablet calendar the day before so that they know exactly what they're doing, but I don't want them seeing what the other engineers are up to either so it has to be individual?
Bit of an ask i'm sure but there must be something out there?
Cheers.
Engineer I Eng1 I Eng2 I Eng3 I Eng4 I
Monday I Job1 I Job5 I Job6 I Job8 I
Tuesday I Job2 I Job7 I Job12 I Job8 I
Wed I Job3 I Job9 I Job11 I Job8 I
Thurs I Job4 I Job10I Job8 I Job8 I
(the I's are meant to be inline but the editer on here won't allow it)
Moving on, the engineers have now been given Samsung Galaxy tablets to use out in the field so I want to update the way that their workload is recorded, is there a calendar that I can setup an individual calendar for each user, but have a view on mine (or another PC based at my work) that I can look at which will list them all, similar to the above?
The plan is that on a daily basis, I will manually sync the diary on my PC with their tablet calendar the day before so that they know exactly what they're doing, but I don't want them seeing what the other engineers are up to either so it has to be individual?
Bit of an ask i'm sure but there must be something out there?
Cheers.